- First 3D Printed Building in Europe – Denmark-based 3D Printhuset finished construction of first 3D printed building in Europe, called The BOD (Building on Demand), situated in Copenhagen
- Massive 3D Printer – Large 3D printer with size 8 x 8 x 6 meters (26 x 26 x 20 foot) was used to print building’s walls in 50 hours
- Other Parts Installation – Team currently installing structure's windows, doors, internal furnishings, and roof
- Project Time Delay – Took twice of estimated time to complete, due to faulty material deliveries and equipment failure related to material handling
- Follows Building Standards – Structure’s wall-cavity will be filled with recycled cellulose fiber to adhere to Denmark’s strict building standards
|